Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 128203007 TxDOT District El Paso County Name Hudspeth Funding Status Funded
Highway RM 1111 Project Length 1.900 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From APPROX 1.9 MI N I10 FRONTAGE ROAD
Work To I10 N FRONTAGE ROAD
Description CONSTRUCT SIDEWALK
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 06/2012 07/2012 08/2012 11/2012 04/2013 05/2013
Actual Date 06/2012 07/2012 02/2013 12/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $85,026.97 $140,467.87
Construction $1,735,244.24 $0.00
Construction EngineeringConstruction Engineering Definition $110,708.58 $0.00
Contingency Contingency Definition $22,384.65
Indirect Indirect Definition $136,216.67
Total Cost $2,089,581.11 $140,467.87