Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 113802015 TxDOT District Pharr County Name Cameron Funding Status Funded
Highway FM 803 Project Length 2.766 Miles Project Type Proposition 14 District Est. Bid Date 2014-Aug
Work From US 77/83 @ RANCHO VIEJO AVENUE
Work To SH 100
Description CONSTRUCT NEW ROAD
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 12/2011
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $330,392.66 $977,663.23
Construction $6,742,707.42 $0.00
Construction EngineeringConstruction Engineering Definition $330,392.66 $0.00
Contingency Contingency Definition $84,283.84
Indirect Indirect Definition $347,249.43
Total Cost $7,835,026.01 $977,663.23