Proposition 12 v2 Project Detail

Data updated on: 6/03/2015 7:56 AM Print This Page
Project Summary
Project ID 105101037 TxDOT District Dallas County Name Ellis Funding Status Unfunded
Highway FM 664 Project Length 3.131 Miles Project Type Traditional District Est. Bid Date 2017-Feb
Work From WESTMORELAND RD
Work To IH 35E IN CITY OF RED OAK
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Maher Ghanayem, P.E. Phone: (214) 320-6691
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 10/2012 05/2015
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,577,062.48 $672,778.53
Construction $32,184,948.61 $0.00
Construction EngineeringConstruction Engineering Definition $1,596,373.45 $0.00
Contingency Contingency Definition $640,480.48
Indirect Indirect Definition $1,847,416.05
Total Cost $37,846,281.07 $672,778.53