Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
097603100 |
TxDOT District |
Houston |
County Name |
Galveston |
Funding Status |
Funded |
| Highway |
FM 518 |
Project Length |
5.376 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Aug |
| Work From |
BAY AREA BLVD |
|
|
| Work To |
FM 2094 |
| Description |
ENHANCEMENT PROJECT |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
12/2011 |
04/2012 |
08/2012 |
04/2013 |
11/2012 |
04/2013 |
04/2013 |
04/2013 |
| Actual Date |
12/2011 |
01/2013 |
01/2013 |
|
|
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$118,109.60 |
$11,874.87 |
| Construction |
$2,410,400.00 |
$0.00 |
Construction Engineering |
$153,783.52 |
$0.00 |
Contingency
 |
$31,094.16 |
|
Indirect
 |
$114,011.92 |
|
| Total Cost |
$2,827,399.20 |
$11,874.87 |
|
 |