Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 097601019 TxDOT District Houston County Name Harris Funding Status Funded
Highway FM 865 Project Length 1.180 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From ALMEDA-GENOA
Work To BW 8
Description WIDEN ROADWAY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 12/2009 11/2010 07/2011 03/2012 07/2011 02/2013 02/2013 02/2013
Actual Date 06/2009 02/2011 02/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $617,400.00 $617,735.13
Construction $12,600,000.00 $0.00
Construction EngineeringConstruction Engineering Definition $624,960.00 $0.00
Contingency Contingency Definition $250,740.00
Indirect Indirect Definition $595,980.00
Total Cost $14,689,080.00 $617,735.13