Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 092106212 TxDOT District Pharr County Name Cameron Funding Status Funded
Highway CS Project Length .650 Miles Project Type Proposition 12 v2 Bid Date 2012-Jun
Work From ON STUART PL RD,FR 0.101 MI S BUS83 Low Bid Amount $1,569,690.00
Work To 0.070 MILES SOUTH OF US 83
Description WIDEN ROADWAY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Construction Company IOC COMPANY LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/12/2012 09/13/2012 95 202 212.63 % 97.79 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $76,914.81 $71,472.62
Construction $1,399,520.23 $1,694,465.90
Construction EngineeringConstruction Engineering Definition $77,856.62 $181,253.22
Contingency Contingency Definition $31,236.83
Indirect Indirect Definition $125,732.17
Total Cost $1,711,260.66 $1,947,191.74