Proposition 12 v2 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 091231270 TxDOT District Houston County Name Brazoria Funding Status Funded
Highway CS Project Length .001 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From PEARLAND PKWY FROM W OF OILER DR
Work To DIXIE FARM RD
Description CONSTRUCT NEW ROAD
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 12/2011 04/2012 08/2012 05/2013 11/2012 06/2014 06/2014 05/2013
Actual Date 12/2011 09/2012 11/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $219,125.44 $361,582.90
Construction $4,471,947.71 $0.00
Construction EngineeringConstruction Engineering Definition $219,125.44 $0.00
Contingency Contingency Definition $55,899.35
Indirect Indirect Definition $211,523.13
Total Cost $5,177,621.07 $361,582.90