Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
078302084 |
TxDOT District |
Lubbock |
County Name |
Lubbock |
Funding Status |
Funded |
| Highway |
LP 289 |
Project Length |
1.620 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jul |
| Work From |
990 FEET EAST OF SLIDE ROAD |
Low Bid Amount |
$26,923,572.74 |
| Work To |
2585 FEET EAST OF QUAKER AVENUE |
| Description |
CONSTRUCT NEW ROADWAY LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Steve Warren, P.E. |
Phone: |
(806) 748-4490 |
| Construction Company |
HAYDON BUILDING CORP. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
03/2010 |
06/2010 |
09/2010 |
01/2011 |
02/2007 |
12/2010 |
12/2010 |
01/2011 |
| Actual Date |
01/2012 |
02/2012 |
03/2012 |
04/2012 |
06/2011 |
04/2012 |
04/2012 |
04/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 09/24/2012 |
11/12/2012 |
581 |
116 |
19.97 % |
26.86 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$1,319,255.06 |
$403,504.19 |
| Construction |
$22,465,448.69 |
$6,670,687.59 |
Construction Engineering |
$1,157,713.63 |
$304,906.19 |
Contingency
 |
$48,462.43 |
|
Indirect
 |
$2,581,970.63 |
|
| Total Cost |
$27,572,850.44 |
$7,379,097.97 |
|
 |