Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 070405020 TxDOT District Childress County Name Motley Funding Status Funded
Highway FM 94 Project Length 7.322 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From 7.357 MILES SW OF NORTHFIELD, NE Low Bid Amount $3,796,505.02
Work To FM 656
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Chuck Steed, P.E. Phone: (940)-937-7191
Construction Company DUININCK, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/09/2012 01/02/2013 209 66 31.58 % 45.84 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $186,028.75 $322,944.11
Construction $3,833,041.78 $1,770,784.42
Construction EngineeringConstruction Engineering Definition $188,306.65 $47,622.43
Contingency Contingency Definition $75,550.45
Indirect Indirect Definition $507,592.72
Total Cost $4,790,520.35 $2,141,350.96