Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
070405020 |
TxDOT District |
Childress |
County Name |
Motley |
Funding Status |
Funded |
| Highway |
FM 94 |
Project Length |
7.322 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Aug |
| Work From |
7.357 MILES SW OF NORTHFIELD, NE |
Low Bid Amount |
$3,796,505.02 |
| Work To |
FM 656 |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Chuck Steed, P.E. |
Phone: |
(940)-937-7191 |
| Construction Company |
DUININCK, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
02/2014 |
02/2014 |
02/2014 |
04/2014 |
02/2014 |
03/2014 |
03/2014 |
04/2014 |
| Actual Date |
02/2011 |
02/2011 |
02/2011 |
04/2011 |
02/2011 |
03/2011 |
|
|
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 11/09/2012 |
01/02/2013 |
209 |
66 |
31.58 % |
45.84 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$186,028.75 |
$322,944.11 |
| Construction |
$3,833,041.78 |
$1,770,784.42 |
Construction Engineering |
$188,306.65 |
$47,622.43 |
Contingency
 |
$75,550.45 |
|
Indirect
 |
$507,592.72 |
|
| Total Cost |
$4,790,520.35 |
$2,141,350.96 |
|
 |