Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 070003125 TxDOT District Austin County Name Travis Funding Status Funded
Highway SH 71 Project Length 1.029 Miles Project Type Proposition 12 v2 Bid Date 2013-Nov
Work From WEST OF THOMAS SPRINGS ROAD Low Bid Amount $15,965,613.32
Work To WEST OF COVERED BRIDGE ROAD
Description CONSTRUCT CENTER TURN LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company JOE BLAND CONSTRUCTION, L.P.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
03/18/2014 289 0 0.00 % 0.00 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $528,078.80 $1,186,150.37
Construction $10,076,174.12 $0.00
Construction EngineeringConstruction Engineering Definition $528,078.80 $315.64
Contingency Contingency Definition $5,388.56
Indirect Indirect Definition $771,139.12
Total Cost $11,908,859.40 $1,186,466.01