Proposition 12 v2 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 066901043 TxDOT District Pharr County Name Hidalgo Funding Status Funded
Highway FM 681 Project Length 1.784 Miles Project Type Proposition 12 v2 Bid Date 2013-Jun
Work From FM 681 (N) @ FM 2221 Low Bid Amount $16,841,116.23
Work To SH 107
Description WIDEN ROADWAY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Construction Company FOREMOST PAVING, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/19/2013 540 42 7.78 % 27.17 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $825,214.69 $487,180.21
Construction $17,241,613.66 $4,805,429.41
Construction EngineeringConstruction Engineering Definition $835,319.37 $105,650.49
Contingency Contingency Definition $335,138.21
Indirect Indirect Definition $867,317.49
Total Cost $20,104,603.42 $5,398,260.11