Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 064803050 TxDOT District Bryan County Name Burleson Funding Status Funded
Highway FM 60 Project Length 3.984 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From 1.2 MILES WEST OF FM 2039
Work To 0.62 MILE EAST OF OLD RIVER
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 01/2002 03/2013 09/2013 01/2014 01/2012 09/2014 11/2013 09/2014
Actual Date 01/2002 02/2013 01/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $578,200.00 $401,371.57
Construction $11,800,000.00 $0.00
Construction EngineeringConstruction Engineering Definition $578,200.00 $0.00
Contingency Contingency Definition $147,500.00
Indirect Indirect Definition $599,440.00
Total Cost $13,703,340.00 $401,371.57