Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
064101033 |
TxDOT District |
Paris |
County Name |
Hunt |
Funding Status |
Funded |
| Highway |
SH 276 |
Project Length |
2.803 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jul |
| Work From |
5.92 MILES EAST OF FM 751 |
Low Bid Amount |
$47,845,878.71 |
| Work To |
0.17 MILES EAST OF FM 513 |
| Description |
REPLACE BRIDGE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Rick Mackey, P.E. |
Phone: |
(903) 737-9375 |
| Construction Company |
WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2010 |
06/2011 |
07/2011 |
02/2012 |
07/2011 |
01/2012 |
01/2012 |
02/2012 |
| Actual Date |
08/2010 |
09/2011 |
02/2012 |
04/2012 |
04/2012 |
04/2012 |
|
04/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/28/2012 |
09/25/2012 |
671 |
120 |
17.88 % |
27.29 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$2,344,448.06 |
$546,094.51 |
| Construction |
$38,496,475.40 |
$13,720,778.24 |
Construction Engineering |
$3,564,517.96 |
$303,621.78 |
Contingency
 |
NaN |
|
Indirect
 |
$3,904,223.70 |
|
| Total Cost |
$48,309,665.12 |
$14,570,494.53 |
|
 |