Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 054801039 TxDOT District Odessa County Name Andrews Funding Status Funded
Highway SH 115 Project Length 1.163 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From SH 176 EAST OF ANDREWS Low Bid Amount $1,860,700.42
Work To 1.2 MI WEST
Description REBUILD ROADWAY
Show Project Location
Contact Information
TxDOT Contact Gary J. Law, P.E. Phone: (432) 332-0501
Construction Company JONES BROS. DIRT & PAVING CONTRACTORS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/24/2012 04/09/2013 100 16 16.00 % 17.78 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $91,174.32 $118,476.12
Construction $1,429,929.00 $12,820.57
Construction EngineeringConstruction Engineering Definition $92,290.74 $17,746.86
Contingency Contingency Definition $37,027.94
Indirect Indirect Definition $229,610.43
Total Cost $1,880,032.43 $149,043.55