Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
054801039 |
TxDOT District |
Odessa |
County Name |
Andrews |
Funding Status |
Funded |
| Highway |
SH 115 |
Project Length |
1.163 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Aug |
| Work From |
SH 176 EAST OF ANDREWS |
Low Bid Amount |
$1,860,700.42 |
| Work To |
1.2 MI WEST |
| Description |
REBUILD ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gary J. Law, P.E. |
Phone: |
(432) 332-0501 |
| Construction Company |
JONES BROS. DIRT & PAVING CONTRACTORS, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
03/2010 |
03/2010 |
08/2010 |
11/2010 |
08/2010 |
10/2010 |
10/2010 |
11/2010 |
| Actual Date |
03/2010 |
06/2010 |
02/2012 |
05/2012 |
04/2012 |
04/2012 |
04/2012 |
05/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 09/24/2012 |
04/09/2013 |
100 |
16 |
16.00 % |
17.78 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$91,174.32 |
$118,476.12 |
| Construction |
$1,429,929.00 |
$12,820.57 |
Construction Engineering |
$92,290.74 |
$17,746.86 |
Contingency
 |
$37,027.94 |
|
Indirect
 |
$229,610.43 |
|
| Total Cost |
$1,880,032.43 |
$149,043.55 |
|
 |