Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 054504046 TxDOT District Tyler County Name Gregg Funding Status Funded
Highway SH 42 Project Length 2.082 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From IH 20 SOUTH RAMP, S
Work To SH 31 IN KILGORE
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 11/2012 01/2013 03/2013 05/2013 04/2013 05/2013 05/2013
Actual Date 10/2012 01/2013 03/2013 01/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $220,500.00 $86,294.72
Construction $4,500,000.00 $0.00
Construction EngineeringConstruction Engineering Definition $305,550.00 $0.00
Contingency Contingency Definition $94,500.00
Indirect Indirect Definition $243,900.00
Total Cost $5,364,450.00 $86,294.72