Project Summary
Project ID 054504046 TxDOT District Tyler County Name Gregg Funding Status Funded
Highway SH 42 Project Length 2.082 Miles Project Type Proposition 12 v2 Bid Date 2013-Jul
Work From IH 20 SOUTH RAMP, S Low Bid Amount $3,692,466.84
Work To SH 31 IN KILGORE
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Construction Company REYNOLDS & KAY, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/17/2013 01/23/2014 88 47 53.41 % 52.80 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $180,930.88 $158,801.73
Construction $3,456,297.36 $1,854,692.97
Construction EngineeringConstruction Engineering Definition $250,718.50 $133,939.64
Contingency Contingency Definition $77,541.80
Indirect Indirect Definition $200,131.70
Total Cost $4,165,620.24 $2,147,434.34