Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
052002037 |
TxDOT District |
Atlanta |
County Name |
Upshur |
Funding Status |
Funded |
| Highway |
SH 155 |
Project Length |
.692 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Jul |
| Work From |
AT SABINE RIVER & SABINE RIVER RELI |
|
|
| Work To |
SOUTH OF BIG SANDY |
| Description |
REPLACE BRIDGE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Dennis M. Beckham, P.E. |
Phone: |
(903) 799-1222 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
11/2009 |
11/2009 |
05/2011 |
07/2011 |
06/2011 |
06/2011 |
06/2011 |
07/2011 |
| Actual Date |
09/2009 |
09/2009 |
04/2011 |
03/2013 |
03/2013 |
|
04/2013 |
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$912,667.33 |
$1,200,948.58 |
| Construction |
$18,625,863.85 |
$0.00 |
Construction Engineering |
$1,357,629.86 |
$0.00 |
Contingency
 |
$95,445.00 |
|
Indirect
 |
$1,067,262.00 |
|
| Total Cost |
$22,058,868.04 |
$1,200,948.58 |
|
 |