Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 052002037 TxDOT District Atlanta County Name Upshur Funding Status Funded
Highway SH 155 Project Length .692 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From AT SABINE RIVER & SABINE RIVER RELI
Work To SOUTH OF BIG SANDY
Description REPLACE BRIDGE
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 11/2009 11/2009 05/2011 07/2011 06/2011 06/2011 06/2011 07/2011
Actual Date 09/2009 09/2009 04/2011 03/2013 03/2013 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $912,667.33 $1,200,948.58
Construction $18,625,863.85 $0.00
Construction EngineeringConstruction Engineering Definition $1,357,629.86 $0.00
Contingency Contingency Definition $95,445.00
Indirect Indirect Definition $1,067,262.00
Total Cost $22,058,868.04 $1,200,948.58