Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
050801335 |
TxDOT District |
Houston |
County Name |
Harris |
Funding Status |
Funded |
| Highway |
IH 10 |
Project Length |
1.150 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Oct |
| Work From |
ON IH 10, FROM N. WAYSIDE TO BW 8 & |
Low Bid Amount |
$1,650,456.27 |
| Work To |
ON IH 610 AT MCCARTY |
| Description |
CONSTRUCT INTERSECTION IMPROVEMENTS |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
| Construction Company |
MAIN LANE INDUSTRIES, LTD. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
12/2010 |
12/2014 |
02/2015 |
06/2015 |
10/2014 |
07/2015 |
08/2015 |
08/2015 |
| Actual Date |
03/2011 |
07/2011 |
11/2011 |
05/2012 |
05/2012 |
03/2012 |
03/2012 |
05/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 11/14/2012 |
|
64 |
22 |
34.38 % |
0.00 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$80,872.36 |
$547,993.43 |
| Construction |
$1,370,366.87 |
$0.00 |
Construction Engineering |
$105,299.11 |
$2,525.01 |
Contingency
 |
$21,290.89 |
|
Indirect
 |
$78,066.58 |
|
| Total Cost |
$1,655,895.81 |
$550,518.44 |
|
 |