Proposition 12 v2 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 050801335 TxDOT District Houston County Name Harris Funding Status Funded
Highway IH 10 Project Length 1.150 Miles Project Type Proposition 12 v2 Bid Date 2012-Oct
Work From ON IH 10, FROM N. WAYSIDE TO BW 8 & Low Bid Amount $1,650,456.27
Work To ON IH 610 AT MCCARTY
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Construction Company MAIN LANE INDUSTRIES, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/14/2012 07/01/2013 64 191 298.44 % 97.70 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $80,872.36 $565,637.92
Construction $1,370,366.87 $1,650,958.70
Construction EngineeringConstruction Engineering Definition $105,299.11 $88,709.54
Contingency Contingency Definition $21,290.89
Indirect Indirect Definition $78,066.58
Total Cost $1,655,895.81 $2,305,306.16