Project ID 050003577 TxDOT District Houston County Name Harris Funding Status Funded
Highway IH 45 Project Length 2.485 Miles Project Type Proposition 12 v2 Bid Date 2013-Feb
Work From AT SHEPHERD Low Bid Amount $24,847,758.14
Work To .
Description INSTALL TRAFFIC MANAGEMENT TECHNOLOGY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Construction Company WEBBER, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/08/2013 01/06/2014 449 217 48.33 % 54.14 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,217,540.15 $2,350,889.93
Construction $22,009,309.09 $14,170,673.10
Construction EngineeringConstruction Engineering Definition $1,165,359.85 $528,710.57
Contingency Contingency Definition $742,947.97
Indirect Indirect Definition $1,175,298.96
Total Cost $26,310,456.02 $17,050,273.60