Proposition 12 v2 Project Detail

Data updated on: 7/06/2015 12:45PM Print This Page
Project Summary
Project ID 050003571 TxDOT District Houston County Name Harris Funding Status Funded
Highway IH 45 Project Length .460 Miles Project Type Traditional District Est. Bid Date 2015-Aug
Work From ALLEN PARKWAY
Work To JEFFERSON STREET
Description INSTALL PAVEMENT STRIPES/MARKERS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 06/2011 03/2012 05/2012 01/2013 03/2013 04/2013 05/2013 05/2013
Actual Date 06/2011 04/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $151,338.02 $992,066.05
Construction $3,088,531.06 $0.00
Construction EngineeringConstruction Engineering Definition $185,003.01 $0.00
Contingency Contingency Definition $80,301.81
Indirect Indirect Definition NaN
Total Cost $3,505,173.90 $992,066.05