Proposition 12 v2 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 042501019 TxDOT District Amarillo County Name Hartley Funding Status Funded
Highway US 87 Project Length 12.463 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From EAST OF US 385 INTERCHANGE Low Bid Amount $21,250,815.21
Work To MOORE COUNTY LINE
Description WIDEN AND REHABILITATE ROADWAY
Show Project Location
Contact Information
TxDOT Contact Gus Khankarli, P.E. Phone: (806) 356-3240
Construction Company RK HALL, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/24/2012 11/19/2012 370 463 123.47 % 63.02 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,041,289.95 $130,254.70
Construction $20,011,529.40 $11,335,841.15
Construction EngineeringConstruction Engineering Definition $1,041,289.95 $430,832.53
Contingency Contingency Definition $10,625.41
Indirect Indirect Definition $2,180,333.64
Total Cost $24,285,068.35 $11,896,928.38