Proposition 12 v2 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 042401045 TxDOT District Tyler County Name Smith Funding Status Funded
Highway SH 31 Project Length 6.631 Miles Project Type Proposition 12 v2 Bid Date 2013-Sep
Work From FM 850, E OF TYLER, E Low Bid Amount $3,431,987.29
Work To FM757
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Construction Company EAST TEXAS BRIDGE, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
12/10/2013 01/13/2014 76 51 67.11 % 23.58 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $168,167.38 $350,197.94
Construction $3,731,667.94 $877,301.15
Construction EngineeringConstruction Engineering Definition $233,031.94 $78,896.63
Contingency Contingency Definition $72,071.73
Indirect Indirect Definition $165,764.99
Total Cost $4,370,703.98 $1,306,395.72