Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 042401045 TxDOT District Tyler County Name Smith Funding Status Funded
Highway SH 31 Project Length 6.353 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From FM 850, E OF TYLER, E
Work To FM757
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 11/2012 01/2013 03/2013 05/2013 04/2013 05/2013 05/2013
Actual Date 11/2011 02/2013 03/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $147,752.44 $270,619.36
Construction $3,015,356.00 $0.00
Construction EngineeringConstruction Engineering Definition $204,742.67 $0.00
Contingency Contingency Definition $63,322.48
Indirect Indirect Definition $163,432.30
Total Cost $3,594,605.89 $270,619.36