Proposition 12 v2 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 040202024 TxDOT District Atlanta County Name Upshur Funding Status Funded
Highway SH 154 Project Length .666 Miles Project Type Proposition 12 v2 Bid Date 2013-Oct
Work From 0.7 MI WEST OF US 259 Low Bid Amount $1,272,043.75
Work To US 259
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Construction Company H. H. HOWARD & SONS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
02/18/2014 03/11/2014 204 95 46.57 % 48.03 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $62,330.14 $193,023.99
Construction $1,128,423.70 $635,133.59
Construction EngineeringConstruction Engineering Definition $62,330.14 $34,906.08
Contingency Contingency Definition $636.02
Indirect Indirect Definition $61,439.71
Total Cost $1,315,159.71 $863,063.66