Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
038007024 |
TxDOT District |
Odessa |
County Name |
Martin |
Funding Status |
Funded |
| Highway |
SH 349 |
Project Length |
16.109 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Sep |
| Work From |
SH 176 |
Low Bid Amount |
$6,430,782.01 |
| Work To |
DAWSON COUNTY LINE |
| Description |
WIDEN AND REHABILITATE ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gary J. Law, P.E. |
Phone: |
(432) 332-0501 |
| Construction Company |
DELHUR INDUSTRIES, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2011 |
10/2011 |
11/2011 |
02/2012 |
02/2012 |
02/2012 |
02/2012 |
02/2012 |
| Actual Date |
08/2011 |
10/2011 |
11/2011 |
05/2012 |
06/2012 |
06/2012 |
08/2011 |
06/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 11/01/2012 |
|
200 |
0 |
0.00 % |
0.89 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$315,108.32 |
$251,231.36 |
| Construction |
$5,489,783.48 |
$62,089.97 |
Construction Engineering |
$318,966.79 |
$10,192.81 |
Contingency
 |
$127,972.56 |
|
Indirect
 |
$536,970.30 |
|
| Total Cost |
$6,788,801.45 |
$323,514.14 |
|
 |