Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
038006015 |
TxDOT District |
Lubbock |
County Name |
Dawson |
Funding Status |
Funded |
| Highway |
SH 349 |
Project Length |
12.781 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Aug |
| Work From |
MARTIN COUNTY LINE |
|
|
| Work To |
THE INTERSECTION OF SH 137 |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Steve Warren, P.E. |
Phone: |
(806) 748-4490 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2012 |
08/2012 |
10/2012 |
01/2013 |
12/2012 |
01/2013 |
01/2013 |
01/2013 |
| Actual Date |
01/2012 |
12/2012 |
03/2013 |
|
07/2012 |
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$841,036.00 |
$663,791.48 |
| Construction |
$17,164,000.00 |
$0.00 |
Construction Engineering |
$851,334.40 |
$0.00 |
Contingency
 |
$341,563.60 |
|
Indirect
 |
$1,249,539.20 |
|
| Total Cost |
$20,447,473.20 |
$663,791.48 |
|
 |