Project ID 037402094 TxDOT District El Paso County Name El Paso Funding Status Funded
Highway US 62 Project Length 5.008 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From 0.663 MI W OF YARBROUGH DR INTERSEC
Work To 0.473 MI E OF LP 375 INTERSECTION
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 07/2011 01/2012 05/2012 03/2013 02/2013 03/2013 08/2012 03/2013
Actual Date 07/2011 05/2012 12/2012 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $225,474.19 $897,680.09
Construction $4,601,514.00 $0.00
Construction EngineeringConstruction Engineering Definition $228,235.09 $0.00
Contingency Contingency Definition $91,570.13
Indirect Indirect Definition $361,218.85
Total Cost $5,508,012.26 $897,680.09