Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
037001033 |
TxDOT District |
Yoakum |
County Name |
Lavaca |
Funding Status |
Funded |
| Highway |
US 77 |
Project Length |
14.415 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jul |
| Work From |
0.20 MI SOUTH OF FM 318 |
Low Bid Amount |
$9,709,623.40 |
| Work To |
1.70 MI NORTH OF SH 111 |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Paul Frerich, P.E. |
Phone: |
(361) 293-4347 |
| Construction Company |
HUNTER INDUSTRIES, LTD. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
06/2010 |
09/2010 |
12/2010 |
03/2011 |
04/2011 |
04/2011 |
|
04/2011 |
| Actual Date |
12/2009 |
12/2009 |
02/2010 |
02/2010 |
02/2011 |
08/2010 |
|
04/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 09/17/2012 |
11/16/2012 |
285 |
72 |
25.26 % |
26.52 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$475,771.55 |
$41,416.36 |
| Construction |
$8,936,511.54 |
$1,953,927.22 |
Construction Engineering |
$475,771.55 |
$79,629.77 |
Contingency
 |
$4,854.81 |
|
Indirect
 |
$773,856.98 |
|
| Total Cost |
$10,666,766.43 |
$2,074,973.35 |
|
 |