Proposition 12 v2 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 035302029 TxDOT District Dallas County Name Denton Funding Status Funded
Highway SH 114 Project Length 4.638 Miles Project Type Proposition 12 v2 Bid Date 2012-Jun
Work From WEST OF COUNTY LINE ROAD Low Bid Amount $28,612,477.14
Work To WEST OF FM 156
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Maher Ghanayem, P.E. Phone: (214) 320-6691
Construction Company SEMA CONSTRUCTION, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/28/2012 04/22/2013 569 281 49.38 % 54.24 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,402,011.38 $3,183,744.68
Construction $30,928,290.98 $13,841,903.72
Construction EngineeringConstruction Engineering Definition $1,419,178.87 $572,054.67
Contingency Contingency Definition $569,388.30
Indirect Indirect Definition $1,699,581.14
Total Cost $36,018,450.67 $17,597,703.07