Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
034103036 |
TxDOT District |
Lufkin |
County Name |
Polk |
Funding Status |
Funded |
| Highway |
US 287 |
Project Length |
8.938 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jun |
| Work From |
3.0 MI E OF US 59 |
Low Bid Amount |
$4,948,703.56 |
| Work To |
TYLER COUNTY LINE |
| Description |
REBUILD ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Cheryl Flood, P.E. |
Phone: |
(936) 633-4349 |
| Construction Company |
BIG CREEK CONSTRUCTION, LTD. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
09/2011 |
10/2011 |
10/2011 |
10/2011 |
03/2012 |
11/2011 |
10/2011 |
03/2012 |
| Actual Date |
09/2011 |
10/2011 |
10/2011 |
04/2012 |
12/2011 |
04/2012 |
04/2012 |
04/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/20/2012 |
09/24/2012 |
244 |
107 |
43.85 % |
41.35 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$242,486.47 |
$57,051.42 |
| Construction |
$5,026,597.83 |
$2,195,945.37 |
Construction Engineering |
$221,701.92 |
$138,073.49 |
Contingency
 |
NaN |
|
Indirect
 |
$410,742.40 |
|
| Total Cost |
$5,901,528.62 |
$2,391,070.28 |
|
 |