Proposition 12 v2 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 034103036 TxDOT District Lufkin County Name Polk Funding Status Funded
Highway US 287 Project Length 8.938 Miles Project Type Proposition 12 v2 Bid Date 2012-Jun
Work From 3.0 MI E OF US 59 Low Bid Amount $4,948,703.56
Work To TYLER COUNTY LINE
Description REBUILD ROADWAY
Show Project Location
Contact Information
TxDOT Contact Cheryl Flood, P.E. Phone: (936) 633-4349
Construction Company BIG CREEK CONSTRUCTION, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/20/2012 09/24/2012 244 107 43.85 % 41.35 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $242,486.47 $57,051.42
Construction $5,026,597.83 $2,195,945.37
Construction EngineeringConstruction Engineering Definition $221,701.92 $138,073.49
Contingency Contingency Definition NaN
Indirect Indirect Definition $410,742.40
Total Cost $5,901,528.62 $2,391,070.28