Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
032708083 |
TxDOT District |
Pharr |
County Name |
Cameron |
Funding Status |
Funded |
| Highway |
US 77 |
Project Length |
3.523 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Aug |
| Work From |
3.7 MI N OF SH 107/FM 508 |
Low Bid Amount |
$4,952,957.41 |
| Work To |
CAMERON/WILLACY COUNTY LINE |
| Description |
CONSTRUCT FRONTAGE ROADS |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Homero Bazan, P.E. |
Phone: |
(956) 702-6214 |
| Construction Company |
FOREMOST PAVING, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
12/2011 |
12/2011 |
01/2012 |
04/2012 |
06/2012 |
03/2012 |
06/2012 |
06/2012 |
| Actual Date |
12/2011 |
12/2011 |
01/2012 |
04/2012 |
07/2012 |
03/2012 |
12/2011 |
07/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/18/2012 |
04/11/2013 |
219 |
34 |
15.53 % |
7.75 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$242,694.91 |
$341,462.14 |
| Construction |
$6,084,230.39 |
$408,139.09 |
Construction Engineering |
$315,998.69 |
$29,200.61 |
Contingency
 |
$63,893.15 |
|
Indirect
 |
$396,731.88 |
|
| Total Cost |
$7,103,549.02 |
$778,801.84 |
|
 |