Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
032702050 |
TxDOT District |
Pharr |
County Name |
Kenedy |
Funding Status |
Funded |
| Highway |
US 77 |
Project Length |
1.578 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jun |
| Work From |
0.87 MI S OF LA PARRA AVE |
Low Bid Amount |
$10,282,198.94 |
| Work To |
0.71 MI N OF LA PARRA AVE |
| Description |
CONSTRUCT OVERPASS/UNDERPASS |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Homero Bazan, P.E. |
Phone: |
(956) 702-6214 |
| Construction Company |
FOREMOST PAVING, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
03/2010 |
05/2010 |
08/2010 |
10/2010 |
07/2011 |
09/2010 |
03/2010 |
07/2011 |
| Actual Date |
06/2010 |
08/2010 |
12/2010 |
02/2011 |
05/2012 |
02/2011 |
06/2010 |
05/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/10/2012 |
09/10/2012 |
340 |
151 |
44.41 % |
54.34 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$503,827.75 |
$318,500.65 |
| Construction |
$8,505,826.64 |
$5,198,668.66 |
Construction Engineering |
$482,235.13 |
$171,569.06 |
Contingency
 |
$307,437.75 |
|
Indirect
 |
$823,604.14 |
|
| Total Cost |
$10,622,931.41 |
$5,688,738.37 |
|
 |