Proposition 12 v2 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 028306022 TxDOT District Wichita Falls County Name Wichita Funding Status Funded
Highway SH 79 Project Length .449 Miles Project Type Proposition 12 v2 Bid Date 2013-Jun
Work From .306 MILES NORTH OF PROFESSIONAL DR Low Bid Amount $554,176.80
Work To .143 MILES SOUTH OF PROFESSIONAL DR
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Danny Brown, P.E. Phone: (940) 720-7740
Construction Company A. L. HELMCAMP, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/19/2013 10/30/2013 60 41 68.33 % 90.69 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $27,154.66 $57,284.28
Construction $365,763.90 $538,768.29
Construction EngineeringConstruction Engineering Definition $27,154.66 $46,481.98
Contingency Contingency Definition $277.09
Indirect Indirect Definition $39,346.55
Total Cost $459,696.86 $642,534.55