Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 028306022 TxDOT District Wichita Falls County Name Wichita Funding Status Funded
Highway SH 79 Project Length .449 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-May
Work From .306 MILES NORTH OF PROFESSIONAL DR
Work To .143 MILES SOUTH OF PROFESSIONAL DR
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Danny Brown, P.E. Phone: (940) 720-7740
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 09/2011 11/2011 05/2012 05/2012 02/2013 05/2012 05/2012 02/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $17,922.43 $55,910.39
Construction $365,763.90 $0.00
Construction EngineeringConstruction Engineering Definition $17,922.43 $0.00
Contingency Contingency Definition $182.88
Indirect Indirect Definition $25,969.24
Total Cost $427,760.88 $55,910.39