Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
027206036 |
TxDOT District |
Brownwood |
County Name |
Lampasas |
Funding Status |
Funded |
| Highway |
US 183 |
Project Length |
12.820 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jun |
| Work From |
US 190, S OF LOMETA |
Low Bid Amount |
$2,650,390.65 |
| Work To |
US 281 N OF LAMPASAS |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Jason Scantling, P.E. |
Phone: |
(325)-643-0415 |
| Construction Company |
KNIFE RIVER CORPORATION - SOUTH |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
10/2011 |
01/2012 |
01/2012 |
03/2012 |
02/2012 |
02/2012 |
02/2012 |
03/2012 |
| Actual Date |
10/2011 |
01/2012 |
01/2012 |
03/2012 |
04/2012 |
03/2012 |
03/2012 |
04/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/10/2012 |
08/29/2012 |
163 |
143 |
87.73 % |
56.29 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$129,869.14 |
$24,497.03 |
| Construction |
$2,660,867.51 |
$1,588,616.96 |
Construction Engineering |
$129,869.14 |
$68,347.26 |
Contingency
 |
$1,325.20 |
|
Indirect
 |
$284,386.92 |
|
| Total Cost |
$3,206,317.91 |
$1,681,461.25 |
|
 |