Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 026901027 TxDOT District Yoakum County Name Fayette Funding Status Funded
Highway US 77 Project Length 2.407 Miles Project Type Proposition 12 v2 Bid Date 2012-Jul
Work From SCHULENBURG SOUTH CITY LIMITS Low Bid Amount $6,078,391.94
Work To LAVACA COUNTY LINE
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Paul Frerich, P.E. Phone: (361) 293-4347
Construction Company HUNTER INDUSTRIES, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/13/2012 12/11/2012 210 211 98.60 % 97.26 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $297,841.20 $106,968.94
Construction $5,634,520.78 $6,332,101.65
Construction EngineeringConstruction Engineering Definition $297,841.20 $215,661.83
Contingency Contingency Definition $3,039.20
Indirect Indirect Definition $484,447.84
Total Cost $6,717,690.22 $6,654,732.42