Proposition 12 v2 Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 025306035 TxDOT District San Antonio County Name Bexar Funding Status Funded
Highway SP 536 Project Length .702 Miles Project Type Proposition 12 v2 Bid Date 2013-Jun
Work From BUSTILLOS DRIVE Low Bid Amount $2,687,291.97
Work To BONNER AVENUE
Description CONSTRUCT CENTER TURN LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Construction Company RELMCO, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/19/2013 06/02/2014 272 66 24.26 % 7.88 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $122,977.94 $541,888.57
Construction $1,977,660.21 $213,850.86
Construction EngineeringConstruction Engineering Definition $160,122.30 $31,398.28
Contingency Contingency Definition $32,375.83
Indirect Indirect Definition $127,997.45
Total Cost $2,421,133.73 $787,137.71