Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 025306035 TxDOT District San Antonio County Name Bexar Funding Status Funded
Highway SP 536 Project Length .702 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jun
Work From BUSTILLOS DRIVE
Work To BONNER AVENUE
Description CONSTRUCT CENTER TURN LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 02/2012 07/2012 09/2012 02/2013 02/2013 02/2013 02/2013 02/2013
Actual Date 02/2012 07/2012 09/2012 01/2013 04/2013 01/2013 01/2013 03/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $96,905.35 $385,453.88
Construction $1,977,660.21 $0.00
Construction EngineeringConstruction Engineering Definition $126,174.72 $0.00
Contingency Contingency Definition $25,511.82
Indirect Indirect Definition $100,860.67
Total Cost $2,327,112.77 $385,453.88