Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 025303068 TxDOT District San Antonio County Name Comal Funding Status Funded
Highway US 281 Project Length .067 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From AT SH 46
Work To .
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 06/2012 10/2012 02/2013 05/2013 05/2013 05/2013 05/2013 05/2013
Actual Date 06/2012 10/2012 04/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $147,000.00 $124,518.64
Construction $3,000,000.00 $0.00
Construction EngineeringConstruction Engineering Definition $191,400.00 $0.00
Contingency Contingency Definition $38,700.00
Indirect Indirect Definition $153,000.00
Total Cost $3,530,100.00 $124,518.64