Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 024805053 TxDOT District Atlanta County Name Upshur Funding Status Funded
Highway US 271 Project Length 1.099 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Jul
Work From AT INT. OF FM 726
Work To .
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 09/2009 10/2009 04/2010 07/2010 04/2010 02/2011 02/2011 02/2011
Actual Date 09/2009 06/2010 07/2011 09/2012 07/2010 09/2012 03/2013 03/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $90,650.04 $214,594.74
Construction $1,850,000.85 $0.00
Construction EngineeringConstruction Engineering Definition $82,695.04 $0.00
Contingency Contingency Definition NaN
Indirect Indirect Definition $106,005.05
Total Cost $2,129,350.98 $214,594.74