Proposition 12 v2 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 024805053 TxDOT District Atlanta County Name Upshur Funding Status Funded
Highway US 271 Project Length 1.099 Miles Project Type Proposition 12 v2 Bid Date 2013-Jul
Work From AT FM 726 Low Bid Amount $1,645,901.51
Work To .
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Construction Company H. H. HOWARD & SONS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/26/2013 01/23/2014 127 80 62.99 % 54.74 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $80,649.17 $223,010.39
Construction $1,841,836.25 $1,014,601.61
Construction EngineeringConstruction Engineering Definition $73,571.80 $65,023.03
Contingency Contingency Definition NaN
Indirect Indirect Definition $94,310.16
Total Cost $2,090,367.38 $1,302,635.03