Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
023803052 |
TxDOT District |
Amarillo |
County Name |
Dallam |
Funding Status |
Funded |
| Highway |
US 54 |
Project Length |
7.128 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jun |
| Work From |
DALHART CURB & GUTTER |
Low Bid Amount |
$6,417,952.70 |
| Work To |
CHAMBERLIN |
| Description |
WIDEN AND REHABILITATE ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Stan Swiatek, P.E. |
Phone: |
(806) 356-3240 |
| Construction Company |
J. LEE MILLIGAN, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
12/2010 |
12/2010 |
12/2010 |
01/2011 |
01/2011 |
01/2011 |
01/2011 |
11/2011 |
| Actual Date |
12/2010 |
01/2011 |
01/2011 |
08/2011 |
09/2011 |
01/2011 |
01/2011 |
09/2011 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/20/2012 |
09/10/2012 |
172 |
159 |
92.44 % |
32.39 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$314,479.69 |
$35,380.40 |
| Construction |
$6,599,032.77 |
$2,224,521.61 |
Construction Engineering |
$314,479.69 |
$114,532.92 |
Contingency
 |
$3,208.98 |
|
Indirect
 |
$658,481.95 |
|
| Total Cost |
$7,889,683.08 |
$2,374,434.93 |
|
 |