Project Summary
Project ID 023505030 TxDOT District San Antonio County Name Uvalde Funding Status Funded
Highway SH 55 Project Length 1.250 Miles Project Type Proposition 12 v2 Bid Date 2013-Jul
Work From 1.25 MI W OF US 83 Low Bid Amount $2,960,802.35
Work To US 83
Description INSTALL/UPGRADE DRAINAGE STRUCTURES
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Construction Company RAY FARIS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/20/2013 01/06/2014 290 109 37.59 % 24.57 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $143,170.42 $185,621.25
Construction $2,455,613.15 $772,473.61
Construction EngineeringConstruction Engineering Definition $186,413.73 $84,088.41
Contingency Contingency Definition $37,691.80
Indirect Indirect Definition $149,014.11
Total Cost $2,971,903.21 $1,042,183.27