Proposition 12 v2 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 023103107 TxDOT District Waco County Name Bell Funding Status Funded
Highway US 190 Project Length 5.948 Miles Project Type Proposition 12 v2 Bid Date 2012-Oct
Work From SP 172 (FT HOOD MAIN GATE) Low Bid Amount $55,361,501.09
Work To WS YOUNG
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company J.D. ABRAMS, L.P.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
12/14/2012 03/04/2013 763 511 66.97 % 63.31 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $2,712,713.55 $6,829,989.93
Construction $55,074,710.79 $35,914,511.21
Construction EngineeringConstruction Engineering Definition $5,536,150.11 $968,137.54
Contingency Contingency Definition $99,650.70
Indirect Indirect Definition $2,402,689.15
Total Cost $65,825,914.30 $43,712,638.68