Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
023001018 |
TxDOT District |
Childress |
County Name |
Collingsworth |
Funding Status |
Funded |
| Highway |
SH 203 |
Project Length |
.200 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Aug |
| Work From |
@ SALT FORK OF RED RIVER |
Low Bid Amount |
$2,895,507.75 |
| Work To |
. |
| Description |
REPAIR BRIDGE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Chuck Steed, P.E. |
Phone: |
(940)-937-7191 |
| Construction Company |
SCR CONSTRUCTION CO., INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
04/2011 |
04/2011 |
05/2011 |
10/2011 |
04/2011 |
04/2011 |
10/2011 |
10/2011 |
| Actual Date |
03/2011 |
03/2011 |
10/2011 |
10/2011 |
10/2011 |
10/2011 |
10/2011 |
10/2011 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 09/24/2012 |
10/29/2012 |
202 |
102 |
50.50 % |
37.59 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$141,879.88 |
$48,869.95 |
| Construction |
$3,726,688.52 |
$1,276,272.16 |
Construction Engineering |
$219,189.94 |
$41,554.84 |
Contingency
 |
$132,614.25 |
|
Indirect
 |
$387,129.39 |
|
| Total Cost |
$4,607,501.98 |
$1,366,696.95 |
|
 |