Proposition 12 v2 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 021804110 TxDOT District Atlanta County Name Cass Funding Status Funded
Highway US 59 Project Length .187 Miles Project Type Proposition 12 v2 Bid Date 2012-Jul
Work From AT EMMA LENNA WAY Low Bid Amount $404,793.97
Work To .
Description INSTALL LEFT TURN LANE AT INTERSECTION
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Construction Company H. V. CAVER, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/21/2012 01/02/2013 52 28 53.85 % 76.26 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $19,834.90 $45,951.25
Construction $344,751.74 $343,095.56
Construction EngineeringConstruction Engineering Definition $25,825.86 $63,863.62
Contingency Contingency Definition $5,221.84
Indirect Indirect Definition $29,873.79
Total Cost $425,508.13 $452,910.43