Proposition 12 v2 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 020507043 TxDOT District Tyler County Name Anderson Funding Status Funded
Highway US 79 Project Length 5.304 Miles Project Type Proposition 12 v2 Bid Date 2012-Sep
Work From 1.6 MI SW OF LP 256 IN PALESTINE, S Low Bid Amount $41,986,850.18
Work To 0.4 MI SW OF FM 645
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Construction Company LONGVIEW BRIDGE AND ROAD, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/24/2012 11/12/2012 880 403 45.80 % 35.28 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $2,057,355.66 $3,491,843.04
Construction $42,809,367.67 $15,920,459.30
Construction EngineeringConstruction Engineering Definition $2,082,547.77 $744,191.13
Contingency Contingency Definition $835,538.31
Indirect Indirect Definition $2,275,687.28
Total Cost $50,060,496.69 $20,156,493.47