Proposition 12 v2 Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 020010079 TxDOT District Beaumont County Name Hardin Funding Status Funded
Highway US 69 Project Length 3.861 Miles Project Type Proposition 12 v2 Bid Date 2014-Aug
Work From SH 327, SOUTH Low Bid Amount $7,502,185.05
Work To ELLIS DRIVE
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Phillip Lujan, P.E. Phone: (409) 898-5740
Construction Company APAC-TEXAS, INC.
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 04/2014 04/2014
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $367,607.07 $471,676.91
Construction $6,958,267.85 $0.00
Construction EngineeringConstruction Engineering Definition $372,108.38 $0.00
Contingency Contingency Definition $149,293.48
Indirect Indirect Definition $362,355.54
Total Cost $8,209,632.32 $471,676.91