Project Summary
Project ID 019302031 TxDOT District San Antonio County Name Kerr Funding Status Funded
Highway SH 39 Project Length 1.267 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From 0.1 MI E OF SH 27 Low Bid Amount $7,644,985.94
Work To NEW INGRAM LAKE DAM
Description REBUILD ROADWAY
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Construction Company RELMCO, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/12/2012 01/21/2013 345 385 111.59 % 49.55 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $374,604.31 $796,047.33
Construction $6,999,685.00 $3,977,281.57
Construction EngineeringConstruction Engineering Definition $519,094.55 $389,068.96
Contingency Contingency Definition $160,544.70
Indirect Indirect Definition $523,681.54
Total Cost $8,577,610.10 $5,162,397.86