Proposition 12 v2 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 018705050 TxDOT District Houston County Name Fort Bend Funding Status Funded
Highway SP 10 Project Length 4.825 Miles Project Type Proposition 12 v2 Bid Date 2013-Aug
Work From US 59 SOUTH Low Bid Amount $19,773,719.85
Work To SH 36
Description CONSTRUCT NEW ROAD
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company J.D. ABRAMS, L.P.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/14/2013 02/20/2014 386 21 5.44 % 9.22 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $751,401.35 $2,712,386.47
Construction $21,999,739.83 $1,865,470.42
Construction EngineeringConstruction Engineering Definition $988,685.99 $54,182.52
Contingency Contingency Definition $1,384,160.39
Indirect Indirect Definition $935,296.95
Total Cost $26,059,284.51 $4,632,039.41