Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 018705050 TxDOT District Houston County Name Fort Bend Funding Status Funded
Highway SP 10 Project Length 4.964 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From US 59 SOUTH
Work To SH 36
Description CONSTRUCT NEW ROAD
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 09/2010 10/2010 09/2011 05/2012 09/2010 05/2012 05/2012 05/2012
Actual Date 09/2010 10/2010 10/2011
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $835,990.11 $2,562,153.16
Construction $21,999,739.83 $0.00
Construction EngineeringConstruction Engineering Definition $1,099,986.99 $0.00
Contingency Contingency Definition $1,539,981.79
Indirect Indirect Definition $1,040,587.69
Total Cost $26,516,286.41 $2,562,153.16