Proposition 12 v2 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 018702064 TxDOT District Yoakum County Name Austin Funding Status Funded
Highway SH 36 Project Length 8.540 Miles Project Type Proposition 12 v2 Bid Date 2012-Aug
Work From SH 159 NORTH OF BELLVILLE Low Bid Amount $10,689,701.03
Work To WASHINGTON COUNTY LINE
Description WIDEN AND REHABILITATE ROADWAY
Show Project Location
Contact Information
TxDOT Contact Paul Frerich, P.E. Phone: (361) 293-4347
Construction Company KNIFE RIVER CORPORATION - SOUTH
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/24/2012 01/14/2013 270 284 100.00 % 87.71 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $523,795.35 $169,719.12
Construction $10,924,806.36 $10,392,282.27
Construction EngineeringConstruction Engineering Definition $523,795.35 $301,127.06
Contingency Contingency Definition $5,344.85
Indirect Indirect Definition $851,969.17
Total Cost $12,829,711.08 $10,863,128.45