Proposition 12 v2 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 017702089 TxDOT District Lufkin County Name San Jacinto Funding Status Funded
Highway US 59 Project Length 1.642 Miles Project Type Proposition 12 v2 Bid Date 2014-Feb
Work From JUST S OF UPRR IN SHEPHERD Low Bid Amount $8,948,536.84
Work To JUST N OF FM 2914
Description CONSTRUCT FRONTAGE ROADS
Show Project Location
Contact Information
TxDOT Contact Cheryl Flood, P.E. Phone: (936) 633-4349
Construction Company TEXAS STERLING CONSTRUCTION CO.
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 10/2011 01/2013 04/2013 04/2013 12/2013 04/2013 04/2013 06/2013
Actual Date 10/2011 01/2013 04/2013 04/2013 12/2013 04/2013 04/2013 06/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $438,478.31 $568,217.64
Construction $8,435,902.09 $0.00
Construction EngineeringConstruction Engineering Definition $425,055.50 $0.00
Contingency Contingency Definition $246,979.62
Indirect Indirect Definition $432,214.33
Total Cost $9,978,629.85 $568,217.64