Proposition 12 v2 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 016608043 TxDOT District Bryan County Name Walker Funding Status Funded
Highway SH 75 Project Length .799 Miles Project Type Proposition 12 v2 Bid Date 2013-May
Work From AT THE INTERCHANGE WITH IH 45 AND Low Bid Amount $8,789,231.37
Work To FM 1791
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Construction Company SMITH & COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/31/2013 11/14/2013 270 115 41.52 % 46.06 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $430,672.34 $622,635.73
Construction $6,810,296.83 $4,137,906.02
Construction EngineeringConstruction Engineering Definition $596,788.81 $227,920.90
Contingency Contingency Definition $184,573.86
Indirect Indirect Definition $446,492.95
Total Cost $8,468,824.79 $4,988,462.65