Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 016608043 TxDOT District Bryan County Name Walker Funding Status Funded
Highway SH 75 Project Length .799 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-May
Work From AT THE INTERCHANGE WITH IH 45 AND
Work To FM 1791
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 03/2011 07/2012 04/2013 07/2013 08/2013 07/2014 07/2014
Actual Date 03/2011 02/2012 03/2012 05/2012 04/2012 05/2012 05/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $333,704.54 $596,707.25
Construction $6,810,296.83 $0.00
Construction EngineeringConstruction Engineering Definition $462,419.15 $156.59
Contingency Contingency Definition $143,016.23
Indirect Indirect Definition $345,963.08
Total Cost $8,095,399.83 $596,863.84