Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
015904034 |
TxDOT District |
San Angelo |
County Name |
Schleicher |
Funding Status |
Funded |
| Highway |
US 277 |
Project Length |
1.470 Miles |
Project Type |
Proposition 12 v2 |
Bid Date |
2012-Jul |
| Work From |
0.42 MILES NORTH OF RM 2129 |
Low Bid Amount |
$6,869,671.05 |
| Work To |
7.3 MI NORTH OF SUTTON COUNTY LINE |
| Description |
CONSTRUCT MERGE LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gary Enos, P.E. |
Phone: |
(325) 947-9233 |
| Construction Company |
REECE ALBERT, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
07/2011 |
09/2011 |
09/2011 |
03/2012 |
03/2012 |
03/2012 |
|
03/2012 |
| Actual Date |
07/2011 |
09/2011 |
12/2011 |
04/2012 |
05/2012 |
04/2012 |
|
05/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 09/24/2012 |
10/12/2012 |
174 |
134 |
77.01 % |
28.24 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$68,696.71 |
$90,926.54 |
| Construction |
$7,329,734.58 |
$2,135,945.58 |
Construction Engineering |
$337,987.81 |
$158,028.24 |
Contingency
 |
$70,757.60 |
|
Indirect
 |
$881,378.80 |
|
| Total Cost |
$8,688,555.50 |
$2,384,900.36 |
|
 |