Proposition 12 v2 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 015902072 TxDOT District San Angelo County Name Tom Green Funding Status Funded
Highway US 277 Project Length 5.713 Miles Project Type Proposition 12 v2 Bid Date 2012-Jul
Work From ALLEN ROAD Low Bid Amount $6,239,473.02
Work To SCHLEICHER COUNTY LINE
Description CONSTRUCT MERGE LANES
Show Project Location
Contact Information
TxDOT Contact Gary Enos, P.E. Phone: (325) 947-9233
Construction Company PRICE CONSTRUCTION, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/17/2012 12/10/2012 179 188 101.08 % 47.07 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $62,394.73 $76,997.06
Construction $5,546,896.18 $3,368,384.24
Construction EngineeringConstruction Engineering Definition $306,982.07 $164,121.64
Contingency Contingency Definition $64,266.58
Indirect Indirect Definition $800,524.39
Total Cost $6,781,063.95 $3,609,502.94